Home › Approvals

Every approval & clearance for Indian power projects

Plain-language guides to all 32 statutory and regulatory approvals for Indian power, solar, wind, BESS and transmission projects — documents, timelines, authorities and process.

R1 · Pre-development approvals

ISTS connectivity & GNA (General Network Access)

Your application to CTUIL for the right to inject power into the national interstate grid — the first gate for any large CTU-connected…

~90 days · CTUIL (Central Transmission Utility)

STU connectivity & evacuation approval

For projects connecting within one state's grid — connectivity approval from the state transmission utility, with different forms, charges…

~75 days · State transmission utility

Discom feasibility approval & registration

The discom checks whether your roof capacity fits your sanctioned load and local network before anything is installed — one portal…

~15 days · Discom (distribution utility)

Net-metering / interconnection agreement

The agreement letting you export solar power to the grid and offset your bill — capacity caps and tariffs differ sharply by state.

~30 days · Discom (distribution utility)

Section 68 prior approval (overhead lines)

Government permission you must hold before installing any higher-voltage overhead line — secure it before even 1% of line work starts.

~60 days · Ministry of Power (via NSWS)

Captive status structuring & annual verification

To escape cross-subsidy and additional surcharges, captive users must hold ≥26% equity and consume ≥51% of generation annually — verified…

~30 days · State nodal / NLDC

State nodal agency registration & single window

Registering your project with the state's renewable-energy nodal agency and single-window portal — the entry ticket for state approvals,…

~21 days · State RE nodal agency

Green energy open access & banking approvals

The approvals to wheel green power to a consumer over the grid — GEOA registration, SLDC/discom concurrence and the state's banking…

~45 days · State nodal (SLDC/STU) / GOAR

R2 · Land & environment

Land title, lease & government land allotment

Securing clear legal rights over the project land — purchase/lease of private land or allotment of government revenue land — before any…

~60 days · Revenue Department / District Collector

Land-use / NA (non-agricultural) conversion

Converting agricultural land for project use — several launch states now exempt solar entirely, others have a fast-track — check your…

~45 days · Revenue Department / District Collector

Forest clearance (forest-land diversion)

Central approval before any forest land is used for your plant, substation or corridor — two stages with afforestation costs; the longest…

~240 days · Forest Department / MoEFCC (PARIVESH)

Forest & wildlife clearance — line route

The same forest-diversion process, scoped to the transmission-line corridor — RoW width is capped by voltage and felling is minimised…

~240 days · Forest Department / MoEFCC (PARIVESH)

Wildlife / NBWL clearance

Extra clearance if your site or route is inside a protected area, a notified eco-sensitive zone, or within 10 km of a national park or…

~270 days · NBWL / MoEFCC

Water drawal NOC (construction & module cleaning)

Permission to draw groundwater (CGWA, via Bhu-Neer portal) or canal water (state irrigation department) for construction and module washing.

~75 days · CGWA / State irrigation department

Tree-cutting permission (non-forest land)

Permission from the Tree Officer/Authority before felling trees on private or revenue land along the route — separate from forest clearance.

~45 days · Tree Officer / Forest & Revenue

R3 · Route & construction authorizations

Section 164 authorization (telegraph-authority powers)

A government order giving your project legal power to place towers and lines on private land without each owner's consent (with…

~150 days · Ministry of Power (via NSWS)

PTCC clearance (power–telecom coordination)

Confirms your power line won't interfere with nearby telecom infrastructure — required before stringing conductors. NOTE: scrapped by MoP…

~90 days · PTCC nodal (DoT/BSNL + CEA)

Right of Way (RoW) compensation process

The rulebook for compensating landowners for towers and the line corridor on land you don't buy — budget for it and run it in step with…

~90 days · District Magistrate / Collector

National Highway crossing permission

Permission to cross a National Highway with your line — applied end-to-end online on Rajmarg Pravesh 2.0, with a built-in 30-day public…

~75 days · NHAI / MoRTH (Rajmarg Pravesh)

State Highway / road crossing permission

The same concept for State Highways and district roads — state-specific, mostly offline to the PWD Executive Engineer with IRC:32 drawings.

~45 days · State PWD

Railway crossing approval

Written railway approval before your line crosses tracks — multi-branch scrutiny, a standard agreement, deposits and a power block for…

~180 days · Indian Railways (zonal)

Water body / canal / river crossing NOC

NOC from the state Irrigation/Water Resources department for towers or spans crossing canals, drains, embankments or rivers — you bear the…

~60 days · Irrigation / Water Resources Department

Existing transmission-line crossing approval

Before your new line crosses an existing power line, the owner of that line must approve your crossing design — and give you a shutdown…

~60 days · Owner utility (POWERGRID / TSP / STU)

Aviation height NOC (AAI via NOCAS)

Height clearance for towers or structures near airports — required in notified areas (~20 km around aerodromes), granted online via the…

~45 days · Airports Authority of India (NOCAS)

Defence NOC (MoD)

Clearance when your site or route is near a defence airfield or establishment — two different tracks, and the least predictable timeline…

~75 days · Ministry of Defence / Local Military Authority

R4 · Electrical safety (build stage)

Pollution consent / SPCB intimation (CTE/CTO)

Pollution-board consents before construction and operation — but solar PV is White category and statutorily EXEMPT from both since…

~45 days · State Pollution Control Board

Fire NOC (substations, control rooms, BESS)

Provisional NOC at plan stage plus final NOC after inspection from State Fire Services — mandatory above height/occupancy thresholds and…

~30 days · State Fire Services

Structural stability certificate (rooftop)

A chartered/structural engineer certifies your roof can carry the panel array and wind loads — quick, but discoms won't process…

~7 days · Chartered structural engineer

CEIG approvals — drawings, inspection & charging (3-touch)

Safety sign-off on your electrical installation in three touches: drawings approved before you build, physical inspection after you build,…

~45 days · State CEIG (Chief Electrical Inspector)

R5 · Pre-commissioning

BESS safety compliance (CEA Chapter XA)

The new national safety regime for battery storage above 650 V — design, fire suppression and a third-party fire audit — notified…

~60 days · CEA / Electrical Inspector

Meter testing & commissioning (discom)

The discom lab tests your bi-directional/smart meter, installs it, and issues the commissioning certificate — the last routine step before…

~21 days · Discom (distribution utility)

R6 · Commissioning & operations

SLDC/RLDC first-time charging & synchronization

The grid operator's go-ahead to energise and synchronise your plant or line to the grid for the first time, then run the trial that makes…

~45 days · SLDC / RLDC (grid operator)

Map my project's full approval roadmap →Should my business switch to green power?