State Highway / road crossing permission — documents, timeline & process

R3 · Route & construction authorizations · ~45 days (indicative)

The same concept for State Highways and district roads — state-specific, mostly offline to the PWD Executive Engineer with IRC:32 drawings.

Application to the concerned PWD division with crossing drawings; restoration charges apply.

Transmission lineSolar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisState highways acts; IRC:32-1969 clearance standards
AuthorityState PWD (Executive/Superintending Engineer); some states via single-window portals
DepartmentState PWD
Indicative timeline~45 days (verify with the authority)
FeesState schedule / restoration charges ⚑ high inter-state variance

Documents required

When is this required?

Complete these first

Solarian expert note

Treat per state — UP uses Nivesh Mitra, Maharashtra uses Aaple Sarkar single-window.

Frequently asked questions

What is State Highway / road crossing permission?

The same concept for State Highways and district roads — state-specific, mostly offline to the PWD Executive Engineer with IRC:32 drawings.

How long does State Highway / road crossing permission take?

Around 45 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants State Highway / road crossing permission?

State PWD (Executive/Superintending Engineer); some states via single-window portals. Department: State PWD.

What documents are required for State Highway / road crossing permission?

Crossing GAD with clearances; Location plan; Restoration charges payment.

When is State Highway / road crossing permission required?

Route crosses a State Highway.

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.