Right of Way (RoW) compensation process — documents, timeline & process

R3 · Route & construction authorizations · ~90 days (indicative)

The rulebook for compensating landowners for towers and the line corridor on land you don't buy — budget for it and run it in step with construction.

Check-survey → DM/DC ascertains land value → (ISTS, on objection) Market Rate Committee with IBBI valuers → one-time upfront digital payment.

Transmission lineSolar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisMoP Guidelines 14-Jun-2024 + Supplementary 21-Mar-2025 (ISTS market-rate mechanism) + Amendment 15-Dec-2025 (valuer methodology)
AuthorityGuidelines by MoP; implemented by District Magistrate/Collector
DepartmentDistrict Magistrate / Collector
Indicative timeline~90 days (verify with the authority)
FeesTower base 200% of land value; corridor 30% baseline (ISTS: 30% rural / 45% urban / 60% metros); valuer fees borne by TSP

Documents required

When is this required?

State-specific notes

Haryana ⚑

States: Haryana

Complete these first

Solarian expert note

Circle-rate disputes and urban stretches drive delays; check whether your state has adopted the 2024 guidelines as-is. ⚑

Frequently asked questions

What is Right of Way (RoW) compensation process?

The rulebook for compensating landowners for towers and the line corridor on land you don't buy — budget for it and run it in step with construction.

How long does Right of Way (RoW) compensation process take?

Around 90 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants Right of Way (RoW) compensation process?

Guidelines by MoP; implemented by District Magistrate/Collector. Department: District Magistrate / Collector.

What documents are required for Right of Way (RoW) compensation process?

Check-survey records; Tower schedule + corridor mapping; Land value ascertainment (circle/market rate); Compensation disbursement records.

When is Right of Way (RoW) compensation process required?

line_involved: yes.

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.