SLDC/RLDC first-time charging & synchronization — documents, timeline & process

R6 · Commissioning & operations · ~45 days (indicative)

The grid operator's go-ahead to energise and synchronise your plant or line to the grid for the first time, then run the trial that makes your power 'firm'.

Joint interconnection study ~6 months before energisation → compliance file → charging clearance → first synchronization → trial run → firm scheduling.

Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESSSolar PV (rooftop)Transmission line

Statutory basis & authority

Statutory basisCERC Indian Electricity Grid Code 2023 (effective 01-Oct-2023) Connection Code; CEA Connectivity Technical Standards 2007
AuthorityRLDC (ISTS-connected) / SLDC (state); RPC coordination
DepartmentSLDC / RLDC (grid operator)
Indicative timeline~45 days (verify with the authority)
FeesNominal per CERC Fees & Charges regulations

Documents required

When is this required?

Complete these first

Solarian expert note

Telemetry/protection non-compliance and un-charged upstream elements are the usual blockers. Infirm power window is ≤1 year from first sync.

Frequently asked questions

What is SLDC/RLDC first-time charging & synchronization?

The grid operator's go-ahead to energise and synchronise your plant or line to the grid for the first time, then run the trial that makes your power 'firm'.

How long does SLDC/RLDC first-time charging & synchronization take?

Around 45 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants SLDC/RLDC first-time charging & synchronization?

RLDC (ISTS-connected) / SLDC (state); RPC coordination. Department: SLDC / RLDC (grid operator).

What documents are required for SLDC/RLDC first-time charging & synchronization?

CEIG/CEA-EI approval; Connection agreement; Protection settings + telemetry/SCADA compliance; Readiness statement.

When is SLDC/RLDC first-time charging & synchronization required?

Connectivity level: CTU (ISTS national grid) / STU (intra-state) / Discom (distribution); Project type: Transmission line.

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.