Home › Approvals › SLDC/RLDC first-time charging & synchronization
SLDC/RLDC first-time charging & synchronization — documents, timeline & process
R6 · Commissioning & operations · ~45 days (indicative)
The grid operator's go-ahead to energise and synchronise your plant or line to the grid for the first time, then run the trial that makes your power 'firm'.
Joint interconnection study ~6 months before energisation → compliance file → charging clearance → first synchronization → trial run → firm scheduling.
Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESSSolar PV (rooftop)Transmission line
Statutory basis & authority
| Statutory basis | CERC Indian Electricity Grid Code 2023 (effective 01-Oct-2023) Connection Code; CEA Connectivity Technical Standards 2007 |
|---|---|
| Authority | RLDC (ISTS-connected) / SLDC (state); RPC coordination |
| Department | SLDC / RLDC (grid operator) |
| Indicative timeline | ~45 days (verify with the authority) |
| Fees | Nominal per CERC Fees & Charges regulations |
Documents required
- CEIG/CEA-EI approval
- Connection agreement
- Protection settings + telemetry/SCADA compliance
- Readiness statement
When is this required?
- First-time charging for grid-connected projects: Connectivity level: CTU (ISTS national grid) / STU (intra-state) / Discom (distribution); Project type: Transmission line (any condition suffices)
Complete these first
- CEIG approvals — drawings, inspection & charging (3-touch) — Safety sign-off on your electrical installation in three touches: drawings approved before you build, physical…
Solarian expert note
Telemetry/protection non-compliance and un-charged upstream elements are the usual blockers. Infirm power window is ≤1 year from first sync.
Frequently asked questions
What is SLDC/RLDC first-time charging & synchronization?
The grid operator's go-ahead to energise and synchronise your plant or line to the grid for the first time, then run the trial that makes your power 'firm'.
How long does SLDC/RLDC first-time charging & synchronization take?
Around 45 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.
Which authority grants SLDC/RLDC first-time charging & synchronization?
RLDC (ISTS-connected) / SLDC (state); RPC coordination. Department: SLDC / RLDC (grid operator).
What documents are required for SLDC/RLDC first-time charging & synchronization?
CEIG/CEA-EI approval; Connection agreement; Protection settings + telemetry/SCADA compliance; Readiness statement.
When is SLDC/RLDC first-time charging & synchronization required?
Connectivity level: CTU (ISTS national grid) / STU (intra-state) / Discom (distribution); Project type: Transmission line.
See also: all approvals · glossary of terms · state roadmaps