CEIG approvals — drawings, inspection & charging (3-touch) — documents, timeline & process

R4 · Electrical safety (build stage) · ~45 days (indicative)

Safety sign-off on your electrical installation in three touches: drawings approved before you build, physical inspection after you build, and charging permission before you energise.

Drawings/SLD submission → scrutiny + fee → construction → pre-commissioning tests → EI site inspection → charging/energisation permission.

Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESSSolar PV (rooftop)Transmission line

Statutory basis & authority

Statutory basisss. 53/162 Electricity Act 2003; CEA (Measures relating to Safety and Electric Supply) Regulations 2023 (in force 15-Jun-2023)
AuthorityState CEIG for intra-state installations
DepartmentState CEIG (Chief Electrical Inspector)
Indicative timeline~45 days (verify with the authority)
FeesState-notified schedules (per kVA/transformer/bay)

Documents required

When is this required?

State-specific notes

Rajasthan

States: Rajasthan

Authority: State Electrical Inspectorate, Energy Department, Rajasthan

Gujarat

States: Gujarat

Authority: Office of the Chief Electrical Inspector, Gujarat

Maharashtra

States: Maharashtra

Authority: Chief Electrical Inspector, Industries/Energy & Labour Department, Maharashtra

Uttar Pradesh

States: Uttar Pradesh

Authority: Directorate of Electrical Safety, Uttar Pradesh

Karnataka

States: Karnataka

Authority: Department of Electrical Inspectorate, Karnataka

Madhya Pradesh ⚑

States: Madhya Pradesh

Authority: Chief Engineer (Electrical Safety) & CEI, GoMP (cei.mp.gov.in)

Chhattisgarh ⚑

States: Chhattisgarh

Authority: Chief Electrical Inspector, GoCG (cei.cg.gov.in)

Andhra Pradesh ⚑

States: Andhra Pradesh

Authority: AP Chief Electrical Inspectorate (ceigap.in / apceig.in)

Tamil Nadu ⚑

States: Tamil Nadu

Authority: Tamil Nadu Electrical Inspectorate (tnei.tn.gov.in) via TNSWP

Haryana ⚑

States: Haryana

Authority: Chief Electrical Inspector, Haryana (ceiharyana.com)

Punjab ⚑

States: Punjab

Authority: Chief Electrical Inspector, Punjab (cei.punjab.gov.in)

Solarian expert note

Drawing resubmissions and inspector scheduling drive the timeline; self-certification applies below state-notified thresholds ⚑ verify per state. Nothing >650 V gets energised without it.

Frequently asked questions

What is CEIG approvals — drawings, inspection & charging (3-touch)?

Safety sign-off on your electrical installation in three touches: drawings approved before you build, physical inspection after you build, and charging permission before you energise.

How long does CEIG approvals — drawings, inspection & charging (3-touch) take?

Around 45 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants CEIG approvals — drawings, inspection & charging (3-touch)?

State CEIG for intra-state installations. Department: State CEIG (Chief Electrical Inspector).

What documents are required for CEIG approvals — drawings, inspection & charging (3-touch)?

SLDs + layout/earthing/protection drawings; Equipment type-test certificates; Licensed contractor + supervisor certificates; Pre-commissioning test reports (IR, earth resistance, relay settings).

When is CEIG approvals — drawings, inspection & charging (3-touch) required?

Project type: Solar PV (rooftop). Project type: Solar PV (ground-mounted) / Wind / Hybrid (solar + wind) / Standalone BESS / Transmission line.

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.