HomeApprovals › Captive status structuring & annual verification

Captive status structuring & annual verification — documents, timeline & process

R1 · Pre-development approvals · ~30 days (indicative)

To escape cross-subsidy and additional surcharges, captive users must hold ≥26% equity and consume ≥51% of generation annually — verified every year, with full back-charges if you fail.

SPV/AoP structuring → shareholding lock → annual verification filing → retroactive confirmation.

Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisRule 3, Electricity Rules 2005; SC Dakshin Gujarat (2023): proportional consumption ±10% per shareholder
AuthorityState nodal (SLDC/discom-appointed) intra-state; NLDC inter-state (CEA verification procedure Feb-2025)
DepartmentState nodal / NLDC
Indicative timeline~30 days (verify with the authority)
FeesAdvisory / filing costs

Documents required

When is this required?

Solarian expert note

Structure the SPV before financial closure — failure at annual verification means full CSS recovery for the year.

Frequently asked questions

What is Captive status structuring & annual verification?

To escape cross-subsidy and additional surcharges, captive users must hold ≥26% equity and consume ≥51% of generation annually — verified every year, with full back-charges if you fail.

How long does Captive status structuring & annual verification take?

Around 30 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants Captive status structuring & annual verification?

State nodal (SLDC/discom-appointed) intra-state; NLDC inter-state (CEA verification procedure Feb-2025). Department: State nodal / NLDC.

What documents are required for Captive status structuring & annual verification?

Shareholding registers; Energy accounts; CA certificates.

When is Captive status structuring & annual verification required?

Business model: captive (own use).

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.