ISTS connectivity & GNA (General Network Access) — documents, timeline & process

R1 · Pre-development approvals · ~90 days (indicative)

Your application to CTUIL for the right to inject power into the national interstate grid — the first gate for any large CTU-connected project.

Online application, 7-day scrutiny, CMETS scheme evolution, in-principle then final grant, BGs and Connectivity Agreement within 1 month, Transmission Delivery Document before physical connection.

Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisCERC Connectivity & GNA Regulations 2022 (amended up to 3rd Amendment, 31-Aug-2025); CTUIL Detailed Procedure (rev. Apr-2026)
AuthorityCTUIL — application via NSWS portal; RLDC/NLDC for T-GNA
DepartmentCTUIL (Central Transmission Utility)
Indicative timeline~90 days (verify with the authority)
FeesApplication fee + Conn-BG1 ₹50 lakh; Conn-BG3 ₹2 lakh/MW; Reg 5.8 BG in lieu of land ₹10 lakh/MW

Documents required

When is this required?

Solarian expert note

Substation margin exhaustion and bay construction lag are the usual delays. SECI bidders: connectivity is a condition precedent — sequence GNA immediately after LOA. ISTS waiver/GNA norms apply — verify current position. ⚑

Frequently asked questions

What is ISTS connectivity & GNA (General Network Access)?

Your application to CTUIL for the right to inject power into the national interstate grid — the first gate for any large CTU-connected project.

How long does ISTS connectivity & GNA (General Network Access) take?

Around 90 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants ISTS connectivity & GNA (General Network Access)?

CTUIL — application via NSWS portal; RLDC/NLDC for T-GNA. Department: CTUIL (Central Transmission Utility).

What documents are required for ISTS connectivity & GNA (General Network Access)?

Online application on NSWS + application fee; Land documents — registered title/lease for 50% of land for applied capacity (or LOA/PPA); Promoter and shareholding details; Generation profile; Conn-BG1 ₹50 lakh, Conn-BG3 ₹2 lakh/MW (Conn-BG2 per bay/ATS cost — waivers per 3rd Amendment).

When is ISTS connectivity & GNA (General Network Access) required?

Project type: Solar PV (ground-mounted) / Wind / Hybrid (solar + wind) / Standalone BESS; Connectivity level: CTU (ISTS national grid).

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.