STU connectivity & evacuation approval — documents, timeline & process

R1 · Pre-development approvals · ~75 days (indicative)

For projects connecting within one state's grid — connectivity approval from the state transmission utility, with different forms, charges and bank guarantees in every state.

Application to the STU, feasibility/system study, preliminary approval, charges and BGs, final approval and connectivity agreement.

Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisState ERC transmission open access / connectivity regulations
AuthorityState transmission utility (STU)
DepartmentState transmission utility
Indicative timeline~75 days (verify with the authority)
FeesState-notified application fee + connectivity charges/BGs

Documents required

When is this required?

State-specific notes

Maharashtra — MSETCL

States: Maharashtra

Authority: MSETCL / Mahatransco (portal mahastu.in; MSEDCL for 11–33 kV)

Basis: MERC Transmission Open Access Regulations 2016 + Mahatransco revised RE-connectivity procedure

Indicative timeline: ~75 days

Rajasthan — RVPN

States: Rajasthan

Authority: RVPN(L) — Rajasthan Rajya Vidyut Prasaran Nigam

Basis: RERC-approved connectivity procedure effective 01-Feb-2026 (≥33 kV)

Indicative timeline: ~75 days

Gujarat — GETCO

States: Gujarat

Authority: GETCO (Gujarat Energy Transmission Corporation)

Basis: GERC Detailed Procedure (Jan-2023) + Order 1 of 2024 (hybrid) + 2025 amendments

Indicative timeline: ~80 days

Karnataka — KPTCL

States: Karnataka

Authority: KPTCL (transmission) / ESCOMs (distribution)

Basis: KERC OA Regulations 2025 + RE Policy 2022–27; KERC draft Connectivity & GNA Regulations 2026 (proposed effective 01-Oct-2026) ⚑

Indicative timeline: ~60 days

Uttar Pradesh — UPPTCL

States: Uttar Pradesh

Authority: UPPTCL (Uttar Pradesh Power Transmission Corporation)

Basis: UPERC Connectivity Regulations 2010 + amendments; UPPTCL Procedure 2013

Indicative timeline: ~45 days

Madhya Pradesh — MPPTCL ⚑

States: Madhya Pradesh

Authority: MPPTCL (Madhya Pradesh Power Transmission Company, Jabalpur)

Basis: MP Electricity Grid Code Revision-III 2024 (Connection Code) + MPERC Intra-State OA Regulations 2021 (6th Amdt Feb-2026)

Indicative timeline: ~75 days

Chhattisgarh — CSPTCL ⚑

States: Chhattisgarh

Authority: CSPTCL (Chhattisgarh State Power Transmission Company, Raipur)

Basis: CSERC (Connectivity and Intra-State Open Access) Regulations 2011 + amendments; Third Amendment draft Jan-2026 (GEOA alignment) ⚑

Indicative timeline: ~75 days

Andhra Pradesh — APTRANSCO ⚑

States: Andhra Pradesh

Authority: APTRANSCO (STU) + discoms ≤33 kV

Basis: AP Grid Code + APERC GEOA Regulation 3 of 2024; APERC clarificatory order Jun-2026

Indicative timeline: ~90 days

Tamil Nadu — TANTRANSCO ⚑

States: Tamil Nadu

Authority: TANTRANSCO (Tamil Nadu Transmission Corporation)

Basis: TNERC Grid Connectivity & Intra-State Open Access Regulations 2014 (Reg 43 procedure, multiple amendments)

Indicative timeline: ~75 days

Haryana — HVPNL ⚑

States: Haryana

Authority: HVPNL (Haryana Vidyut Prasaran Nigam — STU + nodal for connectivity & green OA)

Basis: HERC GEOA Regulations 2023 (Apr-2023) + 1st Amendment (Mar-2025); HVPNL detailed procedure

Indicative timeline: ~45 days

Punjab — PSTCL ⚑

States: Punjab

Authority: PSTCL (Punjab State Transmission Corporation); PSPCL for distribution level

Basis: PSERC Intra-State OA Regulations 2011 (12th/13th Amendments) + PSPCL Detailed Procedure for Grant of Connectivity (03-Apr-2024)

Indicative timeline: ~75 days

Solarian expert note

Process, portal and BG regime differ sharply by state — verify the current state procedure before applying. ⚑

Frequently asked questions

What is STU connectivity & evacuation approval?

For projects connecting within one state's grid — connectivity approval from the state transmission utility, with different forms, charges and bank guarantees in every state.

How long does STU connectivity & evacuation approval take?

Around 75 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants STU connectivity & evacuation approval?

State transmission utility (STU). Department: State transmission utility.

What documents are required for STU connectivity & evacuation approval?

Connectivity application (state format); Project details and single-line diagram; Land/site details; Connectivity charges and voltage-linked BGs as applicable.

When is STU connectivity & evacuation approval required?

Project type: Solar PV (ground-mounted) / Wind / Hybrid (solar + wind) / Standalone BESS; Connectivity level: STU (intra-state).

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.