Forest & wildlife clearance — line route — documents, timeline & process

R2 · Land & environment · ~240 days (indicative)

The same forest-diversion process, scoped to the transmission-line corridor — RoW width is capped by voltage and felling is minimised within the corridor.

Route-scoped forest diversion; trees under conductors kept below clearance height; minimal felling within RoW.

Transmission line

Statutory basis & authority

Statutory basisVan (Sanrakshan Evam Samvardhan) Adhiniyam 1980; CEA Construction Standards Regs 2022 (RoW widths: 132kV:27m · 220kV:35m · 400kV:46m · 765kV:64–67m)
AuthorityMoEFCC via PARIVESH; state forest chain
DepartmentForest Department / MoEFCC (PARIVESH)
Indicative timeline~240 days (verify with the authority)
FeesNPV + CA cost per diverted hectare

Documents required

When is this required?

Solarian expert note

Use the 2025 working-permission window for survey and mobilisation while Stage-II is processed — it explicitly excludes charging.

Frequently asked questions

What is Forest & wildlife clearance — line route?

The same forest-diversion process, scoped to the transmission-line corridor — RoW width is capped by voltage and felling is minimised within the corridor.

How long does Forest & wildlife clearance — line route take?

Around 240 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants Forest & wildlife clearance — line route?

MoEFCC via PARIVESH; state forest chain. Department: Forest Department / MoEFCC (PARIVESH).

What documents are required for Forest & wildlife clearance — line route?

Route KML + forest-land breakup by division; FRA compliance for route villages; CA land proposal; Route alternatives analysis.

When is Forest & wildlife clearance — line route required?

Site or route involves notified forest land; line_involved: yes.

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.