HomeApprovals › Tree-cutting permission (non-forest land)

Tree-cutting permission (non-forest land) — documents, timeline & process

R2 · Land & environment · ~45 days (indicative)

Permission from the Tree Officer/Authority before felling trees on private or revenue land along the route — separate from forest clearance.

Application with tree enumeration; compensatory planting conditions (often 1:10); exempt-species lists vary by state.

Transmission lineSolar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisState tree acts (e.g., Maharashtra Felling of Trees (Regulation) Act 1964 — 60-day decision; Karnataka Preservation of Trees Act 1976)
AuthorityState Tree Officer / Tree Authority (state tree acts)
DepartmentTree Officer / Forest & Revenue
Indicative timeline~45 days (verify with the authority)
FeesNominal + compensatory planting (often 1:10)

Documents required

When is this required?

Conditional: Applies only where trees stand on the route/site — confirm after route survey — verify with the concerned authority.

Solarian expert note

Rajasthan has no general private-land tree act — Tenancy Act restrictions apply instead ⚑.

Frequently asked questions

What is Tree-cutting permission (non-forest land)?

Permission from the Tree Officer/Authority before felling trees on private or revenue land along the route — separate from forest clearance.

How long does Tree-cutting permission (non-forest land) take?

Around 45 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants Tree-cutting permission (non-forest land)?

State Tree Officer / Tree Authority (state tree acts). Department: Tree Officer / Forest & Revenue.

What documents are required for Tree-cutting permission (non-forest land)?

Tree enumeration list (species, girth); Location plan; Compensatory planting undertaking.

Is Tree-cutting permission (non-forest land) always required?

Applies only where trees stand on the route/site — confirm after route survey Verify applicability with the concerned authority.

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.