State nodal agency registration & single window — documents, timeline & process

R1 · Pre-development approvals · ~21 days (indicative)

Registering your project with the state's renewable-energy nodal agency and single-window portal — the entry ticket for state approvals, incentives and (in some states) connectivity itself.

Register the project entity and project on the state nodal portal; the registration/ID is referenced across subsequent state filings.

Solar PV (ground-mounted)WindHybrid (solar + wind)Standalone BESS

Statutory basis & authority

Statutory basisState RE policies and single-window / investment facilitation acts
AuthorityState nodal agency / single-window portal (state-specific)
DepartmentState RE nodal agency
Indicative timeline~21 days (verify with the authority)
FeesState-notified registration fee ⚑

Documents required

When is this required?

State-specific notes

Rajasthan

States: Rajasthan

Authority: RRECL (Rajasthan Renewable Energy Corporation)

Gujarat

States: Gujarat

Authority: GEDA (Gujarat Energy Development Agency)

Maharashtra

States: Maharashtra

Authority: MEDA / MahaUrja (Maharashtra Energy Development Agency)

Uttar Pradesh

States: Uttar Pradesh

Authority: UPNEDA (UP New & Renewable Energy Development Agency)

Madhya Pradesh ⚑

States: Madhya Pradesh

Authority: MPUVNL (MP Urja Vikas Nigam) + RUMSL for solar parks

Chhattisgarh ⚑

States: Chhattisgarh

Authority: CREDA (Chhattisgarh Renewable Energy Development Agency)

Andhra Pradesh ⚑

States: Andhra Pradesh

Authority: NREDCAP — Unified/Single Desk Portal (UPIN tracking)

Karnataka ⚑

States: Karnataka

Authority: KREDL (Karnataka Renewable Energy Development Ltd)

Tamil Nadu ⚑

States: Tamil Nadu

Authority: TNGECL (TEDA + TANGEDCO RE wing merged, operational Jul-2024)

Haryana ⚑

States: Haryana

Authority: HAREDA (Haryana Renewable Energy Development Agency)

Punjab ⚑

States: Punjab

Authority: PEDA (Punjab Energy Development Agency)

Solarian expert note

AI draft — expert review pending. In Rajasthan, RRECL registration is a prerequisite inside the RVPN connectivity flow itself (Feb-2026 procedure).

Frequently asked questions

What is State nodal agency registration & single window?

Registering your project with the state's renewable-energy nodal agency and single-window portal — the entry ticket for state approvals, incentives and (in some states) connectivity itself.

How long does State nodal agency registration & single window take?

Around 21 days as an indicative planning figure. Actual timelines vary by authority workload and application quality — verify with the concerned authority.

Which authority grants State nodal agency registration & single window?

State nodal agency / single-window portal (state-specific). Department: State RE nodal agency.

What documents are required for State nodal agency registration & single window?

Company incorporation + signatory authorization; Project details (capacity, site, technology); Land documents (where held); Registration fee as notified.

When is State nodal agency registration & single window required?

Project type: Solar PV (ground-mounted) / Wind / Hybrid (solar + wind) / Standalone BESS.

Related approvals in this phase

See also: all approvals · glossary of terms · state roadmaps

Map my project's full approval roadmap →Should my business switch to green power?

Indicative guidance from the RegNav knowledge base, expert-verified by Solarian. Not legal advice — always verify with the concerned authority.