Solar & wind project approvals in Uttar Pradesh — complete regulatory roadmap
Everything a developer, EPC or industrial consumer needs to navigate Uttar Pradesh's power-project approvals: the state agencies, open-access and banking rules, net-metering caps, land rules and the state-specific steps layered on top of national approvals.
Key agencies in Uttar Pradesh
| State Transmission Utility (STU) | Uttar Pradesh Power Transmission Corporation Ltd (UPPTCL) |
|---|---|
| Distribution companies (discoms) | PuVVNL, MVVNL, PVVNL, DVVNL and KESCO (under UPPCL) |
| State nodal agency (RE) | Uttar Pradesh New & Renewable Energy Development Agency (UPNEDA) |
| Electricity regulator | Uttar Pradesh Electricity Regulatory Commission (UPERC) |
| Electrical safety (CEIG) | Directorate of Electrical Safety, Government of Uttar Pradesh (Lucknow) — verify the jurisdictional office |
Open access, banking & net metering in Uttar Pradesh
Green energy open access
UP historically applied a 1 MW open-access threshold — a live dispute versus the central 100 kW GEOA rule; verify current practice.
Banking
Banking is restrictive, with peak/off-peak withdrawal limits — verify the applicable UPERC order.
Net metering
Rooftop net metering capped around 2000 kW per current state regulation — verify with the discom.
Worth knowing
UP Solar Policy 2022 grants 100% stamp-duty exemption for solar projects.
Land rules
UP Solar Policy 2022 eases land-use conversion for solar; bundelkhand solar-park land via UPNEDA — verify district-level process. See the national guides for land-use conversion and land title & government allotment.
Approvals with Uttar Pradesh-specific procedures
- STU connectivity & evacuation approval — For projects connecting within one state's grid — connectivity approval from the state transmission utility,…
- Net-metering / interconnection agreement — The agreement letting you export solar power to the grid and offset your bill — capacity caps and tariffs…
- Land-use / NA (non-agricultural) conversion — Converting agricultural land for project use — several launch states now exempt solar entirely, others have…
- CEIG approvals — drawings, inspection & charging (3-touch) — Safety sign-off on your electrical installation in three touches: drawings approved before you build,…
- State nodal agency registration & single window — Registering your project with the state's renewable-energy nodal agency and single-window portal — the entry…
- Green energy open access & banking approvals — The approvals to wheel green power to a consumer over the grid — GEOA registration, SLDC/discom concurrence…
National approvals that apply in Uttar Pradesh
- ISTS connectivity & GNA (General Network Access)
- Land title, lease & government land allotment
- Section 68 prior approval (overhead lines)
- Right of Way (RoW) compensation process
- CEIG approvals — drawings, inspection & charging (3-touch)
- SLDC/RLDC first-time charging & synchronization
Browse all 32 approvals, or generate the exact list for your project:
Map my project's full approval roadmap →Should my business switch to green power?
Frequently asked questions
Who is the State Transmission Utility (STU) in Uttar Pradesh?
Uttar Pradesh Power Transmission Corporation Ltd (UPPTCL). Intra-state (InSTS) connectivity applications for utility-scale projects are made to UPPTCL.
Which agency handles renewable energy approvals in Uttar Pradesh?
Uttar Pradesh New & Renewable Energy Development Agency (UPNEDA) is the state nodal agency; the state regulator is Uttar Pradesh Electricity Regulatory Commission (UPERC).
What are the open access rules in Uttar Pradesh?
UP historically applied a 1 MW open-access threshold — a live dispute versus the central 100 kW GEOA rule; verify current practice. Verify the currently applicable regulation with UPERC.
What are the banking rules for green energy in Uttar Pradesh?
Banking is restrictive, with peak/off-peak withdrawal limits — verify the applicable UPERC order. Banking rules change frequently — verify with the discom/UPERC.
What is the net-metering cap in Uttar Pradesh?
Rooftop net metering is capped around 2000 kW per the state regulation — verify the current cap and any network charges with the discom.
State rules change frequently. This page reflects the RegNav knowledge base — indicative guidance, not legal advice. Verify with UPERC, UPPTCL and the concerned departments.